1911]

PROCEEDINGS OE THE BOARD OE TRUSTEES.

[ENCLOSURE.] ESTIMATED COST OF NECESSARY IMPROVEMENTS IN POWER HOUSE.

103

1. 2. 3. 4. 5. 6. 7. 8.. " 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20.. 21. 22.

Plastering telephone room Painting plaster walls Painting brick and frame walls Cast iron stairs from engineer's office to telephone room. Linoleum for office floor. Sash operating device for monitor windows Lighting fixtures throughout building Gauge beard in engineer's office Awnings for office windows 6" return main through old boiler house Metal lockers 4" Venturi meter on boiler feed line Concrete floor in pump pit Concrete foundation for 120 KW unit Stock room shelving New storage batteries for telephones Moving telephone switchboards to new bldg. New rack for 25 telephones Tirrill voltage regulator New switchboards for 120 and 250 KW units. Motor generator set for new engine room 10,000 feet of electrical conduit

OTHER NEEDED IMPROVEMENTS.

310 25 $ 60 100 90 50 15 125 240 350 80 $ 300 300 600 500 100 . 500 1,500 2,000 700 S 411

,

1.110

6,500

23. Metal lockers to replace present wooden lockers , 24. Paving driveway between engineering and physics bldgs. from Green st. to Springfield avenue 25. Walk along north side of athletic field. , Total.

$3,000 2,200 250 5,450 $13,471

These requests were referred to the Committee on Buildings and Grounds, with power to act. The vote was as follows: Ayes, Mr. Abbott, Mrs. Busey, Mrs. Evans, Mr. Grout, Mr. Hatch, Mr. Hoit, Mr. Meeker; noes, n o n e ; absent, Mr. Anthony, Mrs. Bahrenburg, Mr. Blair, Mr. Deneen, Mr. Moore. President Abbott presented another letter from the supervising architect, as. follows:

. URBANA, luk., March 18, 1911.

Mr. W. L. Abbott, President Board of Trustees: I request the following appropriations for painting and repairs to buildings: 1. Painting walls and ceilings of the lobbies and corridors of the Auditorium $.800 00 2. Painting the under side of the roof of the old Boiler House including the trusses 200 00 3. Painting the under side of Gymnasium roof including trusses 350 00 4. Rebuilding the benches in the north greenhouse of concrete and tile and replacing some of the heating pipes 600 00 5. Elevator gates in Foundry 75 00 6. Painting the exterior of the Observatory 100 00 7. Painting the exterior of the Library 55 00 8. Painting the .exterior of the Law Building > 100 00 9. Painting the exterior of the Chemistry Building 85 00 10. Painting the roof of Natural History Hall 55 00 $2,420 00 Respectfully submitted,

JAMES M. WHITE,