1945]

UNIVERSITY OF ILLINOIS

949

BIDS ON PHYSICS RESEARCH LABORATORY (18) T h e Director of the Physical Plant Department submits the following schedule of bids received December 10 on the general, plumbing, heating and ventilating, and electrical work for the construction of the Physics Research Laboratory Building (betatron). T h e Board of Trustees has authorized the construction of this building on a cost plus fixed fee basis.

GENERAL

Bidder E . N . DeAtley J. P. Cullen & Son John Felmley Co J. L. Simmons Co Kuhne-Simmons Co King & Petry

Check $4 800 4 800 4 800 4 800 4 800 4 800

Prop. 1 General Work $14 643

24 14 11 10

Bond Premium General Only 1% $1 600 00 4 800 00 1 220 25 1%

000 700 500 970

9 725 Prop. 3 Healing and Vent. $4 960 5 58o 4 990 4 46o

PLUMBING AND H E A T I N G

Bidder A. W. Murray Co Reliable Plumbing and Heating Co Carson-Payson Co Champaign Plumbing and Heating Co

Check $1 600 1 600 1 600 1 600

Prop. 2 Plumbing $3 76o 4 2 3° 3 960 3 758

Bond Premium 1% fi88 P. I248 H . {225-58 P. I292.60 H. Prop. 4 Elect. $12 000 9 400 8 000 5 500 8 400

Combined Bid $7 630 6 950

ELECTRICAL W O R K

Bidder Harker & Co Hoffman Electric Co E. A. Koeneman Electric Co Anderson Electric Co Bean Electric Co

491 00 736 5° T h e estimated cost of the actual work, including the fixed fee, is as follows: General work $162,700 Plumbing work 18,800 Heating and ventilating 24,800 Electrical work 49,100

Check $1 500 I 500 1 500 I 500 1 500

Bond Premium Elect. Only 1% $490 00

T h e Director of the Physical Plant Department recommends award of contracts to the lowest bidders as follows: General Work—King and Petry, Champaign, $9,725. Electrical Work—Anderson Electrical Company, Danville, $5,500. T h e Carson-Payson Company, Danville, submitted a combined bid of $6,950 as fee for the plumbing and heating and ventilating work. This is lower than the sum of the lowest bid submitted separately on plumbing and heating and ventilating. T h e Director of the Physical Plant Department recommends that award of the plumbing and the heating and ventilating contracts be deferred pending the advice of the Legal Counsel on the interpretation of which may be considered the lowest bid or lowest bids.

On motion of Mr. Fornof, the award of the contracts for general work to King and Petry and for electrical work to the Anderson Electric Company was authorized, and the awarding of the plumbing and heating and ventilating was referred to the Executive Committee.1

1

See below, page 956.