1969]

UNIVERSITY OF ILLINOIS

351

percentages bid for contractors' fees for replacement of stairway enclosures in University High School, Urbana, the award in each case to the lowest bidder: Estimated Fee PayPer Cent Per Cent Per Cent merits and Total for for for Sub- Equipment Estimated Material Labor contracts Costs Payments General — Skoog Construction Company, Champaign 4 25.5 3 $5 310 ?42 310 Electrical — G. L. Wilsky, an individual doing business as Downtown Electric, Urbana. . 14 23 0 798 4 698 Funds are available in state capital appropriations to the University for 1967-69 and have been released by the Governor. Submitted herewith is a schedule of bids received, a copy of which is being filed with the Secretary of the Board for record.

On motion of Mr. Swain, these contracts were awarded by the following vote: Aye, Mr. Clement, Mr. Grimes, Mr. Hahn, Mr. Hughes, Mr. Jones, Mr. Pogue, Mr. Steger, Mr. Swain; no, none; absent, Governor Ogilvie, Mr. Page, Dr. Weatherly.

REQUEST TO ILLINOIS BUILDING AUTHORITY TO INCREASE CONTRACT FOR CONSTRUCTION OF SCIENCE AND ENGINEERING-SOUTH, PHASE III, CHICAGO CIRCLE (19) The President of the University, with the concurrence of appropriate administrative officers, recommends that the Board of Trustees request the Illinois Building Authority to authorize an increase of $22,922.63 in the contract with Gust K. Newberg Construction Co., Chicago, for foundation work to the Science and Engineering-South building, Chicago Circle. Funds are available in the project budget for this work.

On motion of Mr. Grimes, this recommendation was approved by the following vote: Aye, Mr. Clement, Mr. Grimes, Mr. Hahn, Mr. Hughes, Mr. Jones, Mr. Pogue, Mr. Steger, Mr. Swain; no, none; absent, Governor Ogilvie, Mr. Page, Dr. Weatherly.

REQUEST TO ILLINOIS BUILDING AUTHORITY TO INCREASE CONTRACT FOR CONSTRUCTION OF PHYSICAL EDUCATION BUILDING. PHASE III, CHICAGO CIRCLE (20) The President of the University, with the concurrence of appropriate administrative officers, recommends that the Board of Trustees request the Illinois Building Authority to authorize an increase of $68,788 in the contract with S. N. Nielsen Company, Chicago, for excavation and foundation work to the Physical Education Building, Chicago Circle. Funds are available in the project budget for this work.

On motion of Mr. Grimes, this recommendation was approved by the following vote: Aye, Mr. Clement, Mr. Grimes, Mr. Hahn, Mr. Hughes, Mr. Jones, Mr. Pogue, Mr. Steger, Mr. Swain; no, none; absent, Governor Ogilvie, Mr. Page, Dr. Weatherly.

REQUEST TO ILLINOIS BUILDING AUTHORITY T O CHANGE FINANCING OF CONSTRUCTION OF T H E MEDICAL RESEARCH LABORATORY ADDITION, MEDICAL CENTER (21) On September 18, 1968, the Board of Trustees requested the Illinois Building Authority to contract for construction of the Medical Research Laboratory Addition at the Medical Center campus.