350

BOARD OF TRUSTEES

[March 19

On motion of Mr. Swain, these contracts were awarded by the following vote: Aye, Mr. Clement, Mr. Grimes, Mr. Hahn, Mr. Hughes, Mr. Jones, Mr. Pogue, Mr. Steger, Mr. Swain; no, none; absent, Governor Ogilvie, Mr. Page, Dr. Weatherly.

CONTRACTS FOR AIR CONDITIONING IN ILLINOIS STREET RESIDENCE HALLS. URBANA (16) The President of the University, with the concurrence of appropriate administrative officers, recommends award of the following contracts for air conditioning 592 student rooms and auxiliary lounges, in the Illinois Street Residence Halls on the Urbana campus, the award in each case to the low base bidder: General Work — Skoog Construction Company, Champaign $ 48 700 Air Conditioning Work — Cool-Rite Mechanical Contractors, Inc., Urbana 359 800 Electrical Work — P & S Electric, Champaign 16 000 Total $424 500 Funds for this work are available from the proceeds of the sale of revenue bonds. Submitted herewith is a report of the Physical Plant Planning and Construction Office, including a schedule of bids received, a copy of which is being filed with the Secretary of the Board for record.

On motion of Mr. Clement, these contracts were awarded by the following vote: Aye, Mr. Clement, Mr. Grimes, Mr. Hahn, Mr. Hughes, Mr. Jones, Mr. Pogue, Mr. Steger, Mr. Swain; no, none; absent, Governor Ogilvie, Mr. Page, Dr. Weatherly.

CONTRACTS FOR CONSTRUCTION OF STAIRWAY ENCLOSURES IN METALLURGY AND MINING BUILDING, URBANA (17) The President of the University, with the concurrence of appropriate administrative officers, recommends award of the following cost-plus contracts based on percentages bid for contractors' fees for construction of stairway enclosures in the Metallurgy and Mining Building, Urbana, the award in each case to the lowest bidder: Estimated Fee PayPer Cent Per Cent Per Cent ments and Total for for for Sub- Equipment Estimated Material Labor contracts Costs Payments General — Dean Evans Company, Champaign 2 24 15 $2 460 00 $24 460 00 Electrical—Remco Electrical Corporation, Champaign 5 24.2 0 1 9 7 6 60 13 476 60 Funds are available in state capital appropriations to the University for 1967-69 and have been released by the Governor. Submitted herewith is a schedule of bids received, a copy of which is being filed with the Secretary of the Board for record. O n m o t i o n of M r . S w a i n , t h e s e c o n t r a c t s w e r e a w a r d e d b y t h e following vote: Aye, M r . Clement, M r . Grimes, M r . H a h n , Mr. Hughes, Mr. Jones, Mr. Pogue, Mr. Steger, Mr. S w a i n ; no, none; absent, Governor Ogilvie, M r . P a g e , D r . W e a t h e r l y . CONTRACTS FOR REPLACEMENT OF STAIRWAY ENCLOSURES IN UNIVERSITY HIGH SCHOOL. URBANA (18) The President of the University, with the concurrence of appropriate administrative officers, recommends award of the following cost-plus contracts based on