Repository: UIHistories Project: Board of Trustees Minutes - 1986 [PAGE 362]

Caption: Board of Trustees Minutes - 1986
This is a reduced-resolution page image for fast online browsing.


Jump to Page:
< Previous Page [Displaying Page 362 of 688] Next Page >
[VIEW ALL PAGE THUMBNAILS]




EXTRACTED TEXT FROM PAGE:



1985]

UNIVERSITY OF ILLINOIS

351

On motion of Mrs. Day, this contract was awarded by the following vote: Aye, Mrs. Day, Mr. Forsyth, Mrs. Gravenhorst, Mr. Hahn, Mr. Howard, Mr. Logan, Mr. Madden, Mrs. Shepherd, Miss Smidi; no, none; absent, Governor Thompson. (The student advisory vote was: Aye, Mr. Becker, Mr. Lamm; no, none.)

Contracts, Construction Engineering Research Laboratory, Champaign

(34) T h e president of the University, with the concurrence of the appropriate administrative officers, recommends the award of the following contracts for the construction of a 26,540 square foot addition to the U.S. Army Construction Engineering Research Laboratory. The award in each case is to the low bidder on its base bid plus acceptance of the indicated alternates. 1 Division I — General English Brothers Company, Champaign Base Bid Alt. G-l Alt. G-2 Alt. G-3 Alt. G-4 Alt. G-5 Alt. G-6 $990 9 21 46 12 10 4 000 500 500 000 000 800 200 $1 094 000 Division II — Plumbing Able Mechanical Contractors, Inc., H o m e r . . Base Bid . . Alt. P-2 . . Division III — Heating and Refrigeration A & R Mechanical Contractors, Inc., U r b a n a . Base Bid . . Alt. H-2 . . Division IV — Ventilation R. H. Bishop Company, Champaign 46 400 865 47 265 69 400 2 600 72 000 Base Bid 151 266 575 915 160 756 Division VI— Temperature Control Barber-Colman Company, Springfield Total Base Bid 31 300 $1 538 490 133 169

Division V — Electrical Remco Electrical Corporation, C h a m p a i g n . . Base Bid Alt. E-2 Alt. E-3

It is further recommended that all contracts other than the contract for general work be assigned to the contractor for general work. The project is a one-story addition, to be used as an office building for the staff of a research division, with studio and computer-support spaces and a training center complex. It will be financed from the proceeds of the University of Illinois Revenue Bonds Series 1985B issue. It is also recommended that the firm of Unteed, Scaggs, Nelson, Ltd., Champaign, be employed for basic architectural/engineering services during the construction phase of the project at a rate of 1.61 percent of the actual construction

1

A schedule of the alternates isfiledwith the secretary of the board for record.