144 BOARD OF TRUSTEES [January 15 Report of Award of Contracts, Temple Hoyne Buell Hall, Urfoana (20) On November 13, 1992, the board authorized the comptroller to award construction contracts to the lowest responsible bidder for each division of work for the Temple Hoyne Buell Hall project at the Urbana campus, provided that the total of the bids received would be within the project construction budget of $11,267,000. On November 19 and 24, 1992, bids were received for the Temple Hoyne Buell Hall project and were within the authorized total. The comptroller has approved award of the following contracts. The award in each case is to the lowest responsible bidder on its base bid plus acceptance of the indicated alternates. Division I — General English Brothers Company, Champaign Base Alt. Alt. Alt. Alt. Alt. Alt. Alt. Bid G-l G-2 G-4 G-5 G-6 G-7 G-8 $6 825 000 47 163 9 900 49 000 141 000 22 000 61 000 91 000 $ 7 246 063 Division II — Plumbing Reliable Plumbing 8c Heating Company, Savoy Base Bid Alt. P-l Alt. P-2 311 730 3 395 6 315 321 440 Division III — Heating, Piping, Refrigeration 6? Temperature Control A & R Mechanical Contractors, Inc., Urbana Base Bid Alt. H-l 747 443 9 045 756 488 Division IV — Ventilation and Air Distribution Hart 8c Schroeder Mechanical Contractors, Inc., Champaign Base Bid Alt. V-l Alt. V-2 Division V — Electrical Bodine Electric of Decatur, Inc., Champaign 906 000 12 800 14 800 933 600 Base Bid Alt. E-2 935 463 43 100 978 563
|