I940]

UNIVERSITY OF ILLINOIS & Son 776 00 289 00 065 00 49 00

39

Contract Change Order No. 2 with G. H. Schanbacher Company for painting and interior decorating. (1) Omit finishing of plaster and trim in the fourth story—Deduct $ (2) Omit canvassing walls in ballroom and lounge # 147 (canvas by Owners)—Deduct $1 (3) Additional finishing temporary partitions and permanent doors—Add Net Credit

1 016 00

Contract Change Order No. 11 with English Brothers for general work. (1) Provide additional carpentry work in ground story in accordance with quotation dated June 7, 1940—Add $ 922 22 (2) Provide changes in acoustical ceilings in accordance with quotation dated July 12, 1940— Add 720 66 (3) Provide hanger rods for future installation of balcony at north end of bowling alley, in accordance with quotation dated July 10, 1940 (Quotation 2 ) — A d d 103 50 (4) Additional expense incidental to raising acoustical ceiling over north end of bowling alley in accordance with quotation dated July 12, 1940— Add 139 45 (5) Provide changes in miscellaneous metal work for Space # 3 2 in accordance with quotation dated July 11, 1940—Add 113 41 (6) Provide changes in miscellaneous metal work covered by revised drawings 2-A, 126-A, and 127-A in accordance with quotation dated July 10, 1940—Add 540 02 $2 539 26 (7) Omit silvering on twelve 30" x 64" mirrors, but provide additional transportation in accordance with quotation dated July 10, 1940—Deduct... 15 00 Net Additional Contract Change Order No. II with Phillips, Getschow Company for heating, ventilating, and air conditioning work. Provide convector radiator in main dining room in first story where fireplace was omitted in accordance with quotation dated July 8, 1940—Add Contract Change O r d e r No. 2 with King and Petry for walks and drives. Change approaches to main entrance drive and provide additional concrete walk as indicated on Drawing R-l, and in accordance with quotation of July 17, 1940—Add Contract Change Order No. 7 with English Brothers for general work. (1) Restore honed surface to Fondulac Flagstone Floor in ground story changed by (credit) Items # 3 of Change Order # 2 (2) Omit louvered doors and grilles to Room # 4 0 5 (Credit) Net Additional Cost

2 524 26

158 00

319 50

344 52 90 70 253 82