432

BOARD OF TRUSTEES

[March 20

On motion of Mr. Hughes, these contracts were awarded, as recommended, by the following vote: Aye, Mr. Clement, Mr. Hughes, Mr. Johnston, Mr. Page, Mr. Pogue, Mr. Swain, Mrs. Watkins, Mr. Williamson; no, none; absent, Mr. Dilliard, Mr. Kerner.

CONTRACT FOR RESETTING O F STONEWORK O N ILLINOIS N E U R O P S Y C H I A T R Y INSTITUTE BUILDING

(16) The Director of the Physical Plant and the Vice-President and Comptroller recommend award of a contract for $10,700 to Oman and Giden, Inc., Northfield, Illinois, the lowest bidder, for resetting of stonework along the ambulance drive on the Illinois Neuropsychiatry Institute building. The work will include removing and resetting an extensive area of Indiana limestone used as facing along the ambulance drive which has been loosened by the weather, creating a hazardous condition. Funds are available in the Physical Plant maintenance budget. I concur. O n motion of Mr. Williamson, this contract was awarded by the following vote: Aye, Mr. Clement, M r . Hughes, Mr. Johnston, Mr. Page, M r . Pogue, Mr. Swain, M r s . Watkins, Mr. Williamson; no, none; absent, Mr. Dilliard, Mr. Kerner.

CONTRACTS FOR REMODELING VARIOUS AREAS IN ILLINOIS N E U R O P S Y C H I A T R Y INSTITUTE

(17) The Director of the Physical Plant and the Vice-President and Comptroller recommend award of contracts for miscellaneous remodeling in the Illinois Neuropsychiatric Institute, the award in each case being to the lowest bidder. General — Ashland Construction Company, Chicago $47 00S Base bid $30 956 Additive alternates Service charge for supervision of other contracts assigned to the general contractor I 000 Remodeling Rooms 281 and 282 501 Remodeling Rooms 467 and 468 3 344 Electrical revisions on fourth floor 857 Remodeling Rooms 460, 460A, and 460B 3 378 Remodeling second floor of Neurology area 6 969 Plumbing — Ashland Plumbing and Heating Company, Chicago 9 776 Base bid $ 5 510 Additive alternates Rooms 460, 460A, and 460B 3 850 Second floor Neurology area 416 Electrical — Midwest Interstate Electrical Construction Company, Chicago 21 163 Base bid $14 711 Additive alternates Rooms 281 and 282 118 Rooms 467 and 468 1 180 Electrical revisions, fourth floor 1 378 Rooms 460, 460A, and 460B 587 Second floor Neurology area 3 189 Total Contracts V7 944 The work will include general remodeling in the patient care areas on the second, third, fourth, and fifth floors, including improvements in lighting, relocation of nurses' stations, and rehabilitation of toilet and bath facilities to improve patient care. It is further recommended that all contracts other than the contract for general work be assigned to the contractor for that work, making the total of his contract price $77,944; and that an agreement be entered into with Ashland Construction Company for the assignment of these other contracts for $1,000 which amount is included in the contract price, being the amount bid by that Company