Cost of adding cylinder locks to drawers and doors on laboratory equipment Cost of adding three-hour fire protection to the exterior walls, columns, and ceilings of the mechanical roof penthouse Cost of adding five window air conditioning units Subtotal Plumbing and Sewerage W o r k — Peter H . Smith Co., Chicago Base bid Additive alternate for cost of installation of infrared humidifiers in animal rooms Subtotal Heating, Piping, Refrigeration & Automatic Temperature Control Systems — Herman Bogot & Co., Chicago Base bid Additive alternates f o r : Cost of installation of infrared humidifiers in animal rooms .... Cost of adding five window air conditioning units . Cost of installing a chilled water system and controls in lieu of a direct expansion refrigeration system Subtotal Ventilating — The Robert Irsay Company, Skokie Base bid Additive alternates f o r : Cost of extending exhaust duct branches from the ceiling level to the floor level of the animal r o o m s . . . . Cost of installation of infrared humidifiers in animal rooms Subtotal Electrical •— Gerson Electric Construction Co., Chicago Base bid Additive alternates for: Cost of installation of infrared humidifiers in animal rooms Cost of installing a chilled water system and controls in lieu of a direct expansion refrigeration system Subtotal Total

1 390 00 6 325 00 607 00 $ 86 253 00 $15 579 00 645 00 16 224 00 $58 064 00 5 060 00 2 011 00 3 901 00 69 036 00 $40 872 00 500 00 200 00 41 572 00 $30 199 00 100 00 100 00 30 399 00 $243 484 00

It is further recommended that all contracts other than the general contract be assigned to the contractor for general work, making the total of his contract price $243,484. It is also further recommended that an agreement be entered into with Mutual Contracting Company for the assignment of these other contracts for $4,103, which amount is included in the contract price, being the amount bid by that Company for supervision of other contracts assigned to the general contractor. The work provides for the remodeling of the second and third floors of the Sangamon Street Building, and includes new lighting, air conditioning, and laboratory equipment. The remainder of the funds needed for this work was appropriated by the Board on July 27, 1966. Submitted herewith is the schedule of bids received, a copy of which is being filed with the Secretary of the Board for record. I concur.

On motion of Mr. Clement, these recommendations were approved by the following vote: Aye, Mr. Clement, Mr. Johnston, Mr. Swain; no, none; absent, none.