642

BOARD OF TRUSTEES

[June 13

(The student advisory vote was: Aye, Mr. Malone, Mr. Mathew, Mr. Rose; no, none.)

Contract for Roof Repair and Replacement, Alumni Hall North, Chicago

(34) The chancellor at Chicago recommends the approval of a construction contract for $389,000 with Mark I Waterproofing 8c Restoration Co., Dolton, for roof repair and replacement, Alumni Hall North, at the Chicago campus. Competitive bidding procedures in accordance with the Illinois Purchasing Act were followed; and the award of the contract is to the lowest responsible bidder on the basis of its base bid. The project consists of the removal of selected roofing systems and the installation of a new bitumen roofing system as well as the demolition and removal of parapet wall, skylights and penthouse, rebuilding of parapet wall, and concrete repairs and resealing of coping joints. The total area to be replaced is 8,910 square feet. Funds are available in the Institutional Funds Operating Budget of the Physical Plant Department. A schedule of bids received has been filed with the secretary of the board for the record. The vice president for business and finance concurs. I recommend approval.

On motion of Dr. Gindorf, this recommendation was approved by the following vote: Aye, Dr. Bacon, Mrs. Calder, Mr. Engelbrecht, Dr. Gindorf, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Mrs. O'Malley, Ms. Reese; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Mr. Malone, Mr. Mathew, Mr. Rose; no, none.)

Contract for Roof Repair and Replacement, Behavioral Sciences Building, Chicago

(35) The chancellor at Chicago recommends the award of a construction contract for $529,838 with E. W. Olson Roofing, Inc., Markham, for roof repair and replacement, Behavioral Sciences Building, at the Chicago campus. Competitive bidding procedures in accordance with the Illinois Purchasing Act were followed; and the award of the contract is to the lowest responsible bidder on the basis of its base bid. The project consists of the removal of selected roofing systems and the installation of a new insulation and bitumen roofing system as well as the installation of new metal flashing and roof drains, repair of concrete areas and masonry, and resealing of coping joints. Funds are available in the Institutional Funds Operating Budget of the Physical Plant Department. A schedule of the bids received has been filed with the secretary of the board for the record. The vice president for business and finance concurs. I recommend approval.

On motion of Dr. Gindorf, this recommendation was approved by the following vote: Aye, Dr. Bacon, Mrs. Calder, Mr. Engelbrecht, Dr. Gindorf, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Mrs. O'Malley, Ms. Reese; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Mr. Malone, Mr. Mathew, Mr. Rose; no, none.)