1995]

U N I V E R S I T Y OF ILLINOIS

395

to F. H. Paschen, S. N. Nielsen, Inc., Des Plaines, the lowest responsible bidder on the basis of its base bid ($999,000) plus acceptance of alternates G-4 and G-5 ($59,000 and $5,000, respectively)1 for the ADA compliance modifications to the Chicago Circle Center at the Chicago campus. Funds are available from the Auxiliary Facilities operating budget of the Chicago Circle Center. A schedule of the bids received has been filed with the secretary of the board for record.

On motion of Ms. Reese, this recommendation was approved by the following vote: Aye, Dr. Bacon, Mrs. Calder, Mr. Engelbrecht, Dr. Gindorf, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Mrs. O'Malley, Ms. Reese; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Mr. Malone, Mr. Mathew, Mr. Rose; no, none.)

Increase in Project Budget for Bielfeldt Athletic Administration Building, Urbana

(22) The $6.75 million Bielfeldt Athletic Administration Building is a 37,250 gsf administration building which will house the administrative offices and offices for the majority of men's and women's athletic programs, as well as a Hall of Fame. On July 13, 1995, the board approved the recision of a contract for Bid Group 3, Bid Item #7B, Drywall and Acoustical Ceiling work to Treat Brothers Co., Urbana, in the amount of $383,150; and approved the award of a contract to the second low bidder for the work; namely, Associated Constructors Co., Inc., Bloomington, in the amount of $398,163. Subsequently, in accordance with the Regulations Governing Procurement and Bidding, the University retained the $18,000 bid deposit from Treat Brothers Co., Urbana, which will be added to the project budget. Also, additional funds have been made available to the project for the construction contingency in the amount of $200,000. Accordingly, the president of the University, with the concurrence of the appropriate University officers, recommends that the project budget for the Bielfeldt Athletic Administration Building be increased by $218,000, making the total project budget $6,969,000. Private gift funds for this work are available with the possibility of reimbursement from a subsequent revenue bond sale for the project.

On motion of Ms. Reese, this recommendation was approved by the following vote: Aye, Dr. Bacon, Mrs. Calder, Mr. Engelbrecht, Dr. Gindorf, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Mrs. O'Malley, Ms. Reese; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Mr. Malone, Mr. Mathew, Mr. Rose; no, none.)

Employment of Architect/Engineer for Ambulatory Care Facility, Chicago

(23) On March 9, 1995, the board authorized the employment of Perkins & Will, Chicago, for the professional architectural and engineering services required through the design development phase of the Ambulatory Care Facility at the Chicago campus. On July 13, 1995, the board authorized the employment of the firm for additional design services.

1 Alternate G-4 — Concrete ramps from promenade to pool level; Alternate G-5 — Disabled person pool lift from pool level into pool.