230

Division II — Electrical Bodine Electric of Decatur, Champaign

BOARD OF TRUSTEES

[March 9

Base Bid Alt. #1 Alt. #2

$270 210 55 130 58 900 $ 384 240 $1 033 740

Total

The project will consist of developing playfields at two areas. The first area is on the west side of campus bounded by Oak Street, First Street, Gregory Drive, and a line extending west from Peabody Drive. This area is to be developed into athletic fields, including intramural football fields, soccer fields, basketball courts, sand volleyball courts, and a roller blade hockey court. Fields will be fenced, lit, and irrigated. The site is also to include a service and storage facility. The second area is on the southwest corner of Lincoln and Florida Avenue. The site will contain a fenced soccer field. The award of these contracts will allow the construction of the service and storage facility with supporting mechanical and utility systems and will provide site lighting. Previously awarded was site construction work. Funds are available from the proceeds of the Auxiliary Facilities System Series 1993 Revenue Bond issue. A schedule of the bids received has been filed with the secretary of the board for record.

On motion of Dr. Gindorf, these contracts were awarded by the following vote: Aye, Mr. Engelbrecht, Dr. Gindorf, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Mrs. O'Malley, Ms. Reese; no, none; absent, Dr. Bacon, Mrs. Calder, Governor Edgar. (The student advisory vote was: Aye, Mr. Didato-Castillo, Mr. Rose; no, none.)

Contracts for Stairs and Life Safety Remodeling, lllini Union, Urbana

(16) The president of the University, with the concurrence of the appropriate administrative officers, recommends the award of the following contracts for the stairs and life safety remodeling project in the lllini Union at the Urbana campus. The award in each case is to the lowest responsible bidder on its base bid plus acceptance of the indicated alternates:1 Bid Package # i — General Broeren Russo Construction, Inc., Champaign

Base Bid Alt. #1-1 . . . .

$414 400 81 800 $ 496 200

Bid Package #5 — Fire Protection McDaniel Fire Systems, Champaign

Base Bid Alt. 3-1

140 482 24 354 164 836

Description of Alternates: Alt. 1 - 1 , 4 - 1 , 7 - 1 , 8 - 1 , 9 - 1 , and 10-1 — Upgrade of fire separation of east and west wings of the north building from the central portion to a two-hour fire rating standard; Alt. 3-1 — Add sprinkler zone 3 in the basement.

1