1994]

UNIVERSITY OF ILLINOIS

567

On motion of Dr. Bacon, these recommendations were approved by the following vote: Aye, Dr. Bacon, Mr. Boyle, Mrs. Calder, Dr. Gindorf, Mr. Grabowski, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Ms. Reese; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Ms. Huff; absent, Mr. Riley.) Contracts, Materials Research Facilities, Urbana (27) The president of the University, with the concurrence of the appropriate administrative officers, recommends, subject to approval by the U.S. Department of Education, the award of the following contracts for the renovation of the materials research facilities at the Urbana campus. The award in each case is to the lowest responsible bidder on the basis of its base bid plus acceptance of the indicated alternates. Division I — General Felmley-Dickerson Company, Champaign Base Bid $673 700 Alt. 1 65 000 Alt. 2 16 400 Alt. 4 7 900 Alt. 5 8 100 Alt. 6 6 600 $ 777 700 Division II — Plumbing Commercial Mechanical, Inc., Dunlap Base Bid 367 300 Alt. 2 6 800 Alt. 4 10 600 Alt. 5 8 400 Alt. 6 6 900

400 000 Division III — Heating, Piping, Refrigeration, and Temperature Control Nogle 8c Black Mechanical, Inc., Alt. 3 447 954 70 910 518 864

Division IV — Ventilation and Air Distribution A & R Mechanical Contractors, Inc., Urbana

Base Bid Alt. 2 Alt. 3

328 850 4 800 21 995 355 645