244

BOARD OF TRUSTEES Percent for Material Percent for Labor Percent for Subcontracts

[May 14

Total Estimated Fee Payments

Heating, Piping, and Refrigeration Ruyle Corporation, Peoria Ventilation and Air Distribution Reliable Plumbing 8c Heating Company, Savoy Electrical Glesco Electric, Inc., Urbana Plastering, Plaster Patching, and Repairs Dean Evans Company, Champaign Insulation Champaign A&K Insulation Company, Champaign

5.0

25.0

3.0

$ 17 900

5.0

41.3

2.0

17 120

7.0

35.0

5.0

45 300

10.0

40.0

10.0

40 000

13.0

49.5

5.0

20 950

Funding will be identified on a project-by-project basis and may include State appropriated, institutional, or restricted funds available in the campus operating budget. It is recommended that the comptroller be authorized to approve work orders under these contracts. A schedule of the bids received has been filed with the secretary of the board for record.

On motion of Dr. Bacon, this recommendation was approved by the following vote: Aye, Dr. Bacon, Mr. Boyle, Dr. Gindorf, Mr. Grabowski, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Ms. Reese; no, none; absent, Mrs. Calder, Governor Edgar. (The student advisory vote was: Aye, Mr. Begovich, Mr. Lawless; no, none.)

Increase in Contract, Grainger Engineering Library Information Center, Urbana

(24) On May 14, 1992, the Board of Trustees authorized the award of a construction contract for Bid Item 18 — Plumbing work in the amount of $313,000 to Commercial Mechanical, Inc., Dunlap, for the plumbing work for the construction of the Grainger Engineering Library Information Center at the Urbana campus. Additional site plumbing work is required to complete the uncontracted site work which resulted between the Phase I site plumbing contract and the Phase III building plumbing contract. The construction manager and the architect have recommended and the University concurs that it is in the best interest of the University to do the work. The total cost for this addition to the work to be performed is $45,938. Accordingly, the president of the University, with the concurrence of the appropriate administrative officers, recommends that the contract with Commercial Mechanical, Inc., Dunlap, be increased by $45,938 for the work as described above.