96

BOARD OF TRUSTEES

[October 15

funds (i.e., from State appropriations to the University); and purchases from institutional funds. The latter term designates funds received by the University under contracts with the United States government, private corporations, and other organizations; grants from foundations, corporations, and other donors; and University revolving funds authorized by law. The total amounts of these purchases were: From Appropriated Funds Recommended From Institutional Funds Authorized Recommended Grand Total $ 66 182 2 924 320 2 990 502 $3 240 502 $ 250 000

A complete list of the purchases, with supporting information (including the quotations received), was sent to each member of the board in advance of the meeting. A copy is being filed with the secretary of the board for record.

On motion of Mrs. Shepherd, the purchases authorized by the president were confirmed, and the purchases recommended were authorized by the following vote: Aye, Mr. Boyle, Mrs. Calder, Mr. Downey, Mr. Grabowski, Mrs. Gravenhorst, Mr. Lamont, Ms. Reese, Mrs. Shepherd; no, none; absent, Dr. Bacon, Governor Edgar. (Mrs. Calder asked to be recorded as voting "no" on purchase item nos. 8 and 14.) (The student advisory vote was: Aye, Mr. Begovich, Mr. Lawless; no, none.)

Increase in Contract, Harker Hall Reconstruction, Urbana

(17) On September 12, 1991, the board approved the award of a contract to Anderson Electric, Inc., Mattoon, for the electrical work for the Harker Hall reconstruction project at the Urbana campus. The Foundation, on the recommendation of the campus, has requested that a card-access security system be installed in Harker Hall. This building contains a significant amount of data processing and computer equipment along with confidential donor records. It has been determined that this system will further enhance the building's security. A proposal from the contractor has been received in the amount of $31,350 to install the card-access security system at Harker Hall. The project architect and construction manager have approved the cost of the additional work. Accordingly, the president of the University, with the concurrence of the appropriate administrative officers, recommends that the contract with Anderson Electric, Inc., Mattoon, be increased by $31,350 for the work described. The project construction contract contingency fund will cover the cost. Therefore, no change in the project budget authorization is required. Funds are available from private gift funds through the University of Illinois Foundation.

On motion of Mrs. Shepherd, this recommendation was approved by the following vote: Aye, Mr. Boyle, Mr. Downey, Mr. Grabowski, Mrs. Gravenhorst, Mr. Lamont, Ms. Reese, Mrs. Shepherd; no, Mrs. Calder; absent, Dr. Bacon, Governor Edgar.