UIHistories Project: A History of the University of Illinois by Kalev Leetaru
N A V I G A T I O N D I G I T A L L I B R A R Y
Bookmark and Share



Repository: UIHistories Project: Board of Trustees Minutes - 1920 [PAGE 286]

Caption: Board of Trustees Minutes - 1920
This is a reduced-resolution page image for fast online browsing.


Jump to Page:
< Previous Page [Displaying Page 286 of 902] Next Page >
[VIEW ALL PAGE THUMBNAILS]




EXTRACTED TEXT FROM PAGE:



282

BOARD O F

TRUSTEES

[March 15,

that building as at January 31. That statement indicated that if the cost of the building did not exceed $417,000.00, the amount to be provided from University funds for the biennium 1919-1921 would be about $77,000. I t appears, however, that this estimate of the total cost will probably be exceeded by at least $20,000 if the expected plans for the building are carried out and the building complete finished. The amount necessary to provide therefore in the general budget for 1919-1921 would be $100,000 which would be payable from the expected appropriation of $200,000 from the State Mill Tax. In my opinion, it is highly desirable that the building be completed, and at as early a date as reasonably possible. I would therefore suggest that authority be given for the awarding of additional necessary contracts, as suggested by the Supervising Architect, and than an appropriation of $100,000 or so much thereof as may be necessary, be made from funds for 1919-1921, to complete the building. Cordially yours,

LLOYD MOREY

(d)

Letter from Professor White. March 12, 1919

President E. J, Jamws

DEAR S I R :

We are tabulating below the funds expended, the encumbrances, and additional sums to complete the Smith Memorial Hall. We are also giving the funds available according to the last Comptroller's Report: Total expended to date (approx.) $200,000.00 Encumbrances 105,000.00 Additional to complete 135,000.00 $440,000.00 Funds Available Comptroller's Report—Jan. 31, 1919(approx.) Farm in Champaign County not sold Additional funds necessary to complete Additional funds necessary to complete 310,000.00 30,000.00 $340,000.00 100,000.00

$440,000.00 While we have marked these figures "approximate" they are within $100.00 in each case of the proper values. Yours truly,

JAMES M. W H I T E

Supervising Architect

By C. A. PETRY

The President of the University was authorized to have the Music Building completed as soon as possible.