1977]

UNIVERSITY OF ILLINOIS

215

Amount to B4 PaUhyllu Untntrsily S842 163

New Contracts

With Whom Bolt, Beranek, and Newman, Inc. (subcontract under U S H E W No. 400-76-0116) Dr. Wells Hively (subcontract under U S H E W No. 400-76-0116) Dr. David Rumelhart (subcontract under U S H E W No. 400-76-0116) Total Ptapou Conduct studyonreadingcomprehention withempbajii on the processes involved in learning to read and comprehend during the early and transition level periods Development of improved measures of reading comprehension Research on structural analyses of discourse and cognitivc processes in reading comprehension

10 0 0 0

7 500

$859 663

Change Orders

With Whom Illinois Archaeological Survey United States Agency for International Development: AID/CM/pha-C-73-16 AID/ta-BOA-1109 United States Energy Research and Development Administration EY-76-S-02-2234 United States Navy: N00014-76-C-0745 N00600-75-A-0317 Total Purpcn Archaeological excavation of I.A.S. site 1-148, Iroquois County, Illinois Computer-assisted instruction in population dynamics Assist the government of Ghana in the design of a fiveyear national soybean production, processing, and utilization program Develop techniques of generation and control of cryogenie material particles for use on fusion systems Amount to Bo Paid to Hit Umxnlty S 5 196

44 522 29 295 65 000

Investigate chemiluminescent reactions having a high potential for efficient light production with respect to mechanistic and energetic requirements Provide Naval R O T C educational services

35 000 96 000 $275 013 Amount to Be Paid by tilt Vnivtnity S 7 250

Change Orders

With Whom Barber & DeAtley, Inc. Pmpou Cost-plus contract — general work*. Roofing work on the south half of the south laundry building located on the east side of Orchard Street and one block north of George Huff Drive, Urbana, Illinois Remodeling of the Physical Plant Storage Building

Total

12 550 $ 19 800

Summary

Amount to be paid to the University: Urbana-Champaign Amount to be paid by the University: Medical Center Urbana-Champaign Total $845 146 $ 10 255 879 463 $889 718

This report was received for record. Quarterly Reports of the Comptroller (22) The Comptroller presented his quarterly reports as of September 30 and December 31, 1976. These reports were received for record, and a copy of each has been filed with the Secretary of the Board. Comptroller's Report of Gifts and Funds Received from Outside Sources (23) The Comptroller presented a report of gifts, grants, and contract funds (including funds from private donors and funds received from governmental agen-