996

With Whom United States Army DA-11-177-AV-582 United States Army DA-49-007-MD-421 United States Atomic Energy Commission AT(n-i)-67 Project 5 United States Atomic Energy Commission ATCu-O-67 Project 15 United States Atomic Energy Commission AT(n-i)-3i4 United States Navy N6-ori-07i(5o) United States Navy N6-ori-o7i(53) United States Navy Nobs-72o6o(i7i8) United States Navy Nobs-72i43d7i9) United States Navy Nonr-i834(io) United States Navy Nonr-i834( | i) Hiram Walker & Sons, Inc. With Whom E. T. Drewitch (Plastering)

BOARD OF TRUSTEES

[November 21

Amount to be Paid to the Effective University Date August 2i, 1957 * 2 503 75 37 275 00 25 400 00 28 250 00 10 000 00 1 000 00 14 410 00 30 000 00 20 000 00 14 657 00 21 588 00 720 00 August 31, 1957 September n , 1957 September n , 1957 October io, 1957 August 5, 1957 August 14, 1957 August 27, 1957 August 21, 1957 August 12, 1957 August 23, 1957 September 16, 1957

Purpose Pilot training Transmission of common cold under controlled conditions Atomic energy research and development Diffusionless phase changes in nonferrous metals and alloys Synthesis of boron Noncorrodible anodes Effect of solute atoms and atmospheres on the susceptibility of subgrain boundaries to corrosion Reinforcement of openings in shells and plates Biaxial fatigue properties of high strength materials Hydrodynamic phenomena involved in water-exit Explore the capacity of two measures of counselor acceptance of clients Nutritive properties of dried distillers' solubles in swine nutrition Purpose Seven items: $23.00 to J226.00

Adjustments Made in 1957-58 Cost-Pius Contract

Amount J491 00 Date October, 1957

This report was received for record.

QUARTERLY REPORT OF T H E COMPTROLLER

(14) The Comptroller presents his quarterly report to the Board as of September 30, 1957.

This report was received for record and a copy has been filed with the Secretary of the Board.

CONTRACT FOR THE CONSTRUCTION OF THE DIGITAL COMPUTER LABORATORY (15) On September 12, 1957, bids were received for the construction of the Digital Computer Laboratory. A schedule of these bids has been filed with the Secretary of the Board for record. Because these bids were in excess of available funds they were rejected and confirmation of this action is requested. In the bidding instructions, the University included the standard reservation of the right to reject any or all bids. The drawings and specifications for this building were revised and new bids were taken on November 14. T h e Director of the Physical Plant Department and the Comptroller recommend award of a contract for $338,035 to C. A. Petry and Sons, Inc., Champaign, the lowest bidder. The base bid is $335,660. The contract recommended would include the addition of an alternate for furnishing and installing chalkboards, $1,800, and another for limestone window sills in place of extruded aluminum and masonry panelled construction, $575. The Board of Trustees has already assigned $250,000 from accumulated indirect cost funds for research contracts for this building and an appropriation of $100,000 from the General Reserve fund is being recommended at todays meeting. Funds are also available in the state capital appropriations for 1957-59 for the extension of the Utilities Distribution System to this building. I concur and recommend that the Comptroller and the Secretary of the Board be authorized to execute this contract.