both sides of walks at road intersections and service drives as shown standard steel end protection plates and 8* z 10" oak plank as shown on plans* tlaa* to be securely staked in place with oak stakes and 8 J nails driven into plank on Inside to bond to <d concrete*

48. PROTECT lOJS AMD CUKIMQl

This contractor will provide and maintain suitable barricades with red lanterns to prevent possible injury to the public and for protection of walks*

After concrete i s s e t , t h e walk s h a l l be covered with burlap and same kept wet for a period of five days or walk may be sprinkled so as t o keep i t wet continuously for a period of five days t o promote proper curing of concrete* Calcium chloride may be used dn Luranite slab* 49. FINAL;

At completion of t h i s contract con* t r a c t o r i s t o remove a l l d e b r i s , form lumber* and excess material and earth* leaving grounds* as r e gards sidewalk c o n s t r u c t i o n , i n p e r f e c t c o n d i t i o n . 50* GUARANTY:

All work included in this contract shall be guaranteed as called for in Article 3 of General Conditions.