1949]

UNIVERSITY OF ILLINOIS

951

The repair job was done on this basis and the total cost is now estimated as follows: Crib Farm No. I $ 1 275 53 Tenant Crib Farm No. 1 I 026 48 Barn Farm No. 1 231 71 Crib F a r m No. 3 1 500 06 Crib Farm No. 4 I 841 51 Crib Farm No. 6 I 725 62 Crib Farm No. 7 I 227 21 Crib Farm No. 8 I 337 45 Total $10 165 57 All costs are subject to audit, and payments will be made on the basis of audited costs. Funds are available from the farm operations income. The contract with Mr. Hammerschmidt has been approved by Dean Rusk, has been checked and endorsed by the Legal Counsel and the Director of Nonacademic Personnel, and is submitted by the Comptroller. I recommend approval.

On motion of Dr. Meyer, this work was approved.

CONTRACT FOR REMODELING IN GEORGE HUFF GYMNASIUM (16) The Director of the Physical Plant and the Comptroller recommend award of a contract for $1,800 to E. N. DeAtley, Champaign, the lowest bidder, for the general work in remodeling of space (Room 212) in the George Huff Gymnasium to provide quarters for the work in physical fitness. There is submitted separately a recommendation that a special appropriation of $2,250 be made for this work. I concur and recommend that the Secretarj' of the Board and the Comptroller be authorized to execute this contract.

On motion of Mr. McLaughlin, these recommendations were adopted.

CHANGE IN CONTRACT FOR CONSTRUCTION OF ANIMAL QUARTERS FOR DEPARTMENT OF PHYSIOLOGY (17) A contract for the construction (general work) of animal holding quarters for the Department of Physiology was awarded to Lewis S. Colbert, Champaign, on a cost plus fee basis, under the terms of his standing contract for the year ending June 30, 1949, for minor improvements. The preliminary estimate of cost was $4,700 but the present estimate will exceed this by $1,525. Funds are available in the Physical Plant budget. The Department of Physiology has also requested some additional work (more cages and concrete runways) on these animal quarters, not specified in the original plans. The estimated cost is $4,200 of which $1,800 can be supplied by the Physical Plant Department. There is before the Board a separate recommendation for a supplementary appropriation of $2,400 to the Department of Physiology. It is estimated that the work to be done by the general contractor on this additional construction will cost $1,250. The Director of the Physical Plant and the Comptroller recommend approval of additions to the contract with Lewis S. Colbert of $1,525 to cover the excess over estimated cost, and $1,250 to cover the additional work requested by the Department of Physiology. There have been no previous change orders on this project recommended to the Board. I concur and request that the Comptroller be authorized to execute these contract additions.

On motion of Mrs. Holt, this recommendation was adopted.

ADDITION TO LANDSCAPING CONTRACT FOR SMALL HOMES COUNCIL HOUSING RESEARCH PROJECT (18) The Director of the Physical Plant and the Comptroller recommend an increase of $3,579.65 in the contract with Grundstrom Company, Inc., Glenview, Illinois, for the landscaping of the Small Homes Council Housing Research