BOARD OF TRUSTEES

[October 21

CONTRACT C H A N G E ORDERS O N P.W.A. PROJECTS (11) A recommendation from the Director of the Physical Plant Department that the following contract change orders be authorized: Illini Union Building Contract Change Order No. 12 with the Phillips, Getschow Company for heating, ventilating, and air conditioning work. (1) Change controls and motor drive on five automatic air filters $100 oo (2) Material and labor necessary to installation of two Johnson traps 29 90 Total Additional Cost $129 00 Contract Change Order No. 14 with English Brothers for general work. (1) Provide interior metal double sliding screens for windows in place of exterior wood screens in accordance with quotation dated September 10, 1940—Deduct $205 5° (2) Provide only prime finish on frames for paint by others—Deduct 20 40 Total Deduction $225 90 Contract Change Order No. 9 with the A r t h u r W . Murray Company for plumbing work. Provide plumbing work necessary to connecting up refrigeration compressors in connection with food service for the building— Add $350 08

SUMMARY

Total additions Total deductions Net Addition

$480 88 225 00 $254 98

On motion of Mr. Williamson, these change orders were approved, by the following vote: Aye, Mr. Adams, Mr. Cleary, Mr. Jensen, Mr. Karraker, Mrs. Plumb, Mr. Pogue, Mr. Williamson; no, none; absent, Mr. Mayer, Dr. Meyer, Mr. Stelle, Mr. Wieland.

COMPTROLLER'S REPORT OF CONTRACTS (12) T h e Comptroller's report of minor contracts executed under general regulations of the Board of Trustees:

CONTRACTS EXECUTED BY THE COMPTROLLER SEPTEMBER 18 TO OCTOBER 14, 1040 Amount to be paid by With Whom For the University Illinois Central Railroad Maintenance of track to New $45 per year Company Power Plant

Date June 21, 1940

This report was received for record.

QUARTERLY REPORT OF THE COMPTROLLER (13) T h e quarterly report of the Comptroller to the Board of Trustees as at September 30, 1940. A copy of this report has been sent to each member of the Board. This report was referred to the Finance Committee.