270

BOARD OF TRUSTEES

[December 19

Plumbing — Ashland Plumbirig and Heating Company, Chicago $ 10 387 00 Heating and Process Piping—William Adams Engineers, Inc., Chicago 9 934 00 Ventilating — Corite-Reynolds Corporation, Des Plaines 13 710 00 Pipe Covering and Insulation — Chicago Pipe and Boiler Covering Company, Chicago 1 670 00 Electrical — Fries-Walters Company, Chicago 10 618 00 Laboratory Equipment — Browne-Morse Company, Chicago 24 326 00 Total $106 755 25 It is further recommended that all contracts other than the contract for general work be assigned to the contractor for that work, making the total of his contract price $106,755.25; and that an agreement be entered into with DugganKarasik Construction Company for the assignment of these other contracts for $3,532.25 which amount is included in the contract price, being the amount bid by that Company for service charge for supervision of other contracts assigned to the general contractor. Funds are available in the state capital appropriations to the University for 1961-63 from the Universities Building Fund and have been released and from a matching National Institutes of Health Grant (RC-1068). Submitted herewith is a schedule of all bids received and a copy is being filed with the Secretary of the Board for record. I concur.

On motion of Mrs. Watkins, these contracts were awarded, as recommended, by the following vote: Aye, Mr. Clement, Mr. Dilliard,

Mr. Johnston, Mr. Pogue, Mr. Swain, Mrs. Watkins, Mr. Wilkins,

Mr. Williamson; no, none; absent, Mr. Hughes, Mr. Kerner.

CONTRACTS FOR REMODELING IN RESEARCH AND EDUCATIONAL HOSPITALS (14) T h e Director of the Physical Plant and the Vice-President and Comptroller recommend award of contracts for remodeling an area of the basement of the Research and Educational Hospitals (General Hospital) for use as locker rooms and for storage of medical records, the award in each case being to the lowest responsible bidder. General — B. R. Abbot Construction Company, Chicago $49 914 Base bid $46 789 Additive alternates Service charge for supervision of other contracts assigned to this contractor 1 800 Suspended ceiling, Medical Records area 1 260 Air conditioning, Medical Records area 65 Plumbing — Fettes, Love, and Sieben, Inc., Chicago 8 443 Heating — Phillips, Getschow Company, Chicago 5 215 Base bid $ 4 200 Additive alternate for air conditioning, Medical Records area 1 015 Ventilating — Narowetz Heating and Ventilating Company, C h i c a g o . . . 20 946 Base bid ....... $17 573 Additive alternate for air conditioning, Medical Records area 3 373 Electrical — Local Electric Company, Inc., Chicago 15 065 Base bid ........ $15 000 Additive alternate for air conditioning, Medical Records area 65 Total $99 583 A low bid submitted by the Thunderbird Electric Company, Chicago, would have to be rejected because of the Company's admitted failure to meet the standard conditions in the Board of Trustees "Regulations Governing Procurement and Bidding at the University of Illinois." T h e Company has therefore been permitted to withdraw its bid, and the electrical contract is being awarded to the Local Electric Company, Inc., Chicago, as the lowest responsible bidder.