UIHistories Project: A History of the University of Illinois by Kalev Leetaru
N A V I G A T I O N D I G I T A L L I B R A R Y
Bookmark and Share



Repository: UIHistories Project: Board of Trustees Minutes - 1964 [PAGE 309]

Caption: Board of Trustees Minutes - 1964
This is a reduced-resolution page image for fast online browsing.


Jump to Page:
< Previous Page [Displaying Page 309 of 1633] Next Page >
[VIEW ALL PAGE THUMBNAILS]




EXTRACTED TEXT FROM PAGE:



264

BOARD OF TRUSTEES

ADJOURNMENT OF NOVEMBER MEETING

[December 19

The Board of Trustees at its meeting on November 9, 1962, recessed for luncheon and the program in dedication of the Radio Telescope in Danville, but did not reconvene. On motion of Mr. Johnston, the November meeting adjourned.

INTRODUCTION OF MR. RAY PAGE

President Clement announced that Mr. Ray Page, Superintendent of Public Instruction-Elect, was present, having been invited to attend today's meeting as a guest of the Board of Trustees. Mr. Page was introduced by Mr. Wilkins.

MINUTES APPROVED

The Secretary presented the minutes of the meeting of the Board of Trustees on June 20, 1962, press proof copies of which had previously been sent to the Board. On motion of Mr. Swain, the minutes were approved as printed on pages 1499 to 1973, inclusive.

REPORT OF THE EXECUTIVE COMMITTEE

The Secretary presented the following report:

C o n t r a c t s for E q u i p m e n t for H e a t i n g P l a n t at C o n g r e s s Circle T h e Board of Trustees at its meetings on May 24 and June 20, 1962, awarded contracts for equipment for the heating plant to be constructed on the Congress Circle campus, but reserved the right of the University in each case to terminate the contract prior to September 15, 1962, and without cost to the University, by giving the contractor written notice of such termination. The Executive Committee was authorized to act for the Board on negotiations with contractors in exercising the University's right to terminate contracts or to extend the period during which they may be executed or terminated. The Executive Committee on August 16, 1962, extended the period in which the contracts may be executed or terminated to December 15, 1962. Taking of bids for other construction on the Congress Circle Campus has now been postponed, so that it would be to the University's advantage to extend further the dates within which the University may execute or terminate the contracts for the heating plant. The Executive Committee reports that, on recommendation of the Director of the Physical Plant, the Vice-President and Comptroller, and the President of the University, it has authorized the extension of the period within which the following contracts may be executed, or terminated, to and including March 15, 1963. T h e contractors concerned have agreed to this extension. High temperature water boilers, hot water pumps, and erection — International Boiler W o r k s Company, East Stroudsburg, Pennsylvania.. .$235 597 Refrigeration equipment — T. F. Hanley Corporation, Chicago 185 859 Condenser water and chilled water circulating pumps — Allis-Chalmers Manufacturing Company, Chicago 20 493 Cooling tower — Floor Products Company, Oak P a r k 39 230 Switchgear and electrical equipment 15 K V switchgear — Allis-Chalmers Manufacturing Company 38 200 5 K V switchgear — Allis-Chalmers Manufacturing Company 44 800 480 V substation — Allis-Chalmers Manufacturing Company 29 650 125-volt battery — Allis-Chalmers Manufacturing Company 5 794 Inverter-diverter and control panel — Allis-Chalmers Manufacturing Company 8 851 T h e Committee has also authorized termination of the following contracts with General Electric Company in view of the Company's policy that price escalation clauses would be applicable to these contracts if extended beyond December 15, 1963.