1967]

UNIVERSITY OF ILLINOIS

321

CONTRACTS FOR REMODELING SPACE VACATED BY PEDIATRICS FOR CENTER FOR HANDICAPPED C H I L D R E N , GENERAL HOSPITAL BUILDING, MEDICAL CENTER (20) The Director of the Physical Plant and the Vice-President and Comptroller recommend the award of contracts for remodeling space vacated by the Department of Pediatrics in the General Hospital Building, which will be used by the Center for Handicapped Children, the award in each case being to the lowest bidder: General — Heller Construction Company, Inc., Chicago Base bid $33 771 00 Deductive alternate for substitution of vinyl asbestos floor covering for carpet floor covering —1 000 00 $32 771 00 Ventilation — Crone Associates, Inc., Chicago 12 676 00 Plumbing — Fettes, Love & Sieben, Inc., Chicago 4 162 00 Pipe Covering and Insulation — Western Asbestos Company, Inc., Chicago 2 1S3 00 Electrical — Midwest Interstate Electrical Construction Co., Chicago Base bid $22 563 00 Deductive alternate for omission of intercommunication equipment —3 070 00 19 493 00 Heating, Refrigeration, and Temperature Controls — A. Kilander & C o , Inc., Chicago 15 744 00 Total $86 999 00 The work consists of rehabilitating the area by providing partitioning and a suspended ceiling; raising the lighting level; providing equipment space and a new air conditioning system. Funds for this project are available to the Division of Services for Crippled Children. Submitted herewith is a schedule of bids received, a copy of which is being filed with the Secretary of the Board for record. I concur.

On motion of Mrs. Watkins, these contracts were awarded by the following vote: Aye, Mr. Clement, Mr. Dilliard, Mr. Hughes, Mr. Johnston, Mr. Page, Mr. Pogue, Mr. Swain, Mrs. Watkins, Mr. Williamson; no, none; absent, Mr. Jones, Governor Kerner.

REQUEST TO ILLINOIS BUILDING AUTHORITY TO INCREASE CONTRACT FOR CONSTRUCTION OF CHICAGO CIRCLE CAMPUS. PHASE II (21) The Director of the Physical Plant and the Vice-President and Comptroller recommend that the Illinois Building Authority be requested to authorize an increase of $134,567.58 in the contract with Gust K. Newberg Construction C o , Chicago, for the construction of Chicago Circle campus, Phase II. This additional cost is based on the necessity of extending caissons beyond the depth shown on the contract documents for the Library Addition ($49,456.32) and the Science and Engineering Staff Offices Building ($85,111.26) to reach solid rock for caisson support. The depths shown on the drawings were determined as a result of analysis of soil borings prior to the preparation of working drawings. Soil conditions experienced in construction at the planned depth required additional excavation to reach "solid rock," thus resulting in additional costs in construction. The amounts are based on a unit price of $900 per additional cubic yard excavated included in the bid and contract documents. Funds are available to the Illinois Building Authority for this work. I concur.

On motion of Mr. Swain, this change in contract was authorized by the following vote: Aye, Mr. Clement, Mr. Dilliard, Mr. Hughes, Mr. Johnston, Mr. Page, Mr. Pogue, Mr. Swain, Mrs. Watkins, Mr. Williamson; no, none; absent, Mr. Jones, Governor Kerner.