1971]

UNIVERSITY OF ILLINOIS

219

General Work—Jim H. and Glenwood Gladney, doing business as Gladney Brothers, Champaign 2.5 21.65 2 $5 128 35 $61 028 35 Electrical Work—Remco Electrical Corporation, Champaign 10 29.3 10 1 622 00 10 122 00 Plumbing Work — Willis and W. C. Thomas, a Partnership, doing business as Thomas Plumbing & Heating Co., Urbana 16 33 0 2 780 00 13 780 00 Heating, Piping, Refrigeration, and Automatic Temperature Control Systems Work— Reliable Plumbing & Heating Co., Champaign 20 45 5 4 400 00 16 400 00 Total $101 330 35 Funds for this work are available in a grant from the State of Illinois Law Enforcement Commission. Submitted herewith is a schedule of bids received, a copy of which is being filed with the Secretary of the Board for record.

Estimated Fee PayPer ments Per Cent Cent Per Cent Rentals and Total for for for Sub- Equipment Estimated Material Labor contracts Costs Payments

On motion of Mr. Swain, these contracts were awarded by the following vote: Aye, Mr. Clement, Mr. Grimes, Mr. Hahn, Mr. Hughes, Mr. Jones, Mr. Pogue, Mr. Steger, Mr. Swain, Dr. Walker; no, none; absent, Dr. Bakalis, Governor Ogilvie.

CONTRACT FOR U N D E R G R O U N D PIPING WORK FOR STEAM A N D CHILLED WATER TO LEVIS FACULTY CENTER, URBANA

(18) The President of the University, with the concurrence of appropriate administrative officers, recommends award of a contract in the amount of $144,500 to Cool-Rite Mechanical Contractors, Inc., Urbana, the low bidder on the base bid plus the additive alternate. This work will provide for underground piping for steam and chilled water service to the Levis Faculty Center at the UrbanaChampaign campus. Funds are available in state capital appropriations to the University and have been released by the Governor. O n motion of Mr. Swain, this contract was awarded by the following vote: Aye, Mr. Clement, Mr. Grimes, Mr. H a h n , Mr. Hughes, M r . Jones, M r . Pogue, Mr. Steger, M r . Swain, D r . W a l k e r ; no, n o n e ; absent, Dr. Bakalis, Governor Ogilvie.

REQUEST TO ILLINOIS BUILDING AUTHORITY TO CONTRACT FOR IMPROVEMENTS AT ABBOTT POWER PLANT, URBANA

(19) The President of the University, with the concurrence of appropriate administrative officers, recommends that the Illinois Building Authority be requested to award the following contracts for improvements to Boilers S, 6, and 7 at the Abbott Power Plant at the Urbana-Champaign campus, the award in each case being to the low base bidder. Piping and Miscellaneous Mechanical Work — Gallaher & Speck, Chicago $321 144 Electrical Installation Work — Aldridge Electric Inc., Libertyville 94 139 General Work — Dean Evans Co., Champaign 78 727

$494 010