1970]

UNIVERSITY OF ILLINOIS Additive Alternate No. 1

143

Contractor Base Bids Total Automatic Burner Control Equipment — Memeco, Inc., Chicago $107 377 $ 1 3S0 $108 727 Automatic Combustion Control Equipment — Beckman Instruments, Inc., Lincolnwood.. $ 43 688 $ 43 688 The project is part of the construction for the Urbana-Champaign campus which the Board of Trustees at its meeting on September 17, 1969, requested the Illinois Building Authority to provide. The Authority will finance the construction and lease the facilities to the University. Funds for rental payments are available in state appropriations to the University. Attached herewith is a report of the Office of Physical Plant Planning and Construction including a schedule of bids received, a copy of which is being filed with the Secretary of the Board for record.

On motion of Mr. Hahn, this recommendation was approved by the following vote: Aye, Mr. Clement, Mr. Hahn, Mr. Hughes, Mr. Jones, Mr. Pogue, Mr. Swain, Dr. Walker; no, none; absent, Mr. Grimes, Governor Ogilvie, Mr. Page, Mr. Steger.

LEASE AND ASSIGNMENT OF ARCHITECTURAL CONTRACT TO THE ILLINOIS BUILDING AUTHORITY FOR BURRILL HALL A D D I T I O N , URBANA

(12) The Seventy-sixth General Assembly declared the Burrill Hall Building Addition at the Urbana-Champaign campus to be in the public interest and thereby indicated the funding of this project could be accomplished by the Illinois Building Authority. The declaration also provides that the cost of any specific project can exceed the amount set forth so long as the aggregate amount stated therein to be financed by the Authority for the University is not exceeded. The Illinois Building Authority Act contemplates that a transfer of jurisdiction of the property on which the project is to be constructed will be made to the Authority and that the lease agreement between the Authority and the University will be executed, providing for the construction of the specified project by the Authority and its use by the University. Funds for the payment of rental to the Authority during the current fiscal year are available in state appropriations to the University. The President of the University, with the concurrence of appropriate administrative officers, recommends adoption of the following resolutions authorizing the Comptroller and the Secretary of the Board of Trustees to make, execute, acknowledge, and deliver the necessary lease, instrument of transfer, and other documents between the University and the Illinois Building Authority to accomplish the purposes stated. On July 23, 1969, the Board of Trustees authorized the employment of Fugard, Orth & Associates, Inc., Chicago, for architectural services for the construction of this project at a fee of seven per cent of the actual cost of construction including supervision. It is further recommended that authorization be given for the assignment of the architectural contract with Fugard, Orth & Associates, Inc., to the Illinois Building Authority. Resolution WHEREAS, the Illinois Building Authority, a body corporate and politic of the State of Illinois created by the General Assembly of the State of Illinois, is empowered to acquire by purchase or otherwise, construct, complete, remodel, maintain, and equip any and all buildings and other facilities as the General Assembly by law declares to be in the public interest; WHEREAS, in accordance with the Illinois Building Authority Act, the Seventysixth General Assembly of the State of Illinois has declared the following University of Illinois project at the Champaign-Urbana campus to be in the public interest: Construct Burrill Hall Building Addition $ 1 382 750