88

BOARD OF TRUSTEES

[September

11

Funds are available from Fiscal Year 1987 State appropriated funds and Institutional Funds budget of the Chicago Physical Plant A schedule of the bids received has been filed with the secretary of the board for record. O n motion of Miss Smith, these contracts were awarded by the following vote: Aye, Mrs. Day, Mr. Forsyth, Mrs. Gravenhorst, Mr. Hahn, Mr. Howard, Mr. Logan, Mr. Madden, Mrs. Shepherd, Miss Smith; no, none; absent, Governor Thompson. (The student advisory vote was: Aye, Mr. Filip, Mr. Starkeson; no, none.) Contracts, Parking Control Facility, Parking Lot No. 9, Chicago (29) The president of the University, with the concurrence of the appropriate administrative officers, recommends the award of contracts as shown below for the construction of a parking control facility (traffic building) for the new parking lot facility recently constructed at the northeast corner of Harrison and Morgan Streets, Chicago campus. The award in each case is to the low base bidder. This project consists of construction of a one-story, 266 square foot masonry building with entry drives, parking lot control gates, sidewalks, curbing, and storm and sanitary sewer connections. The project is the second phase of the recently completed 350-space parking lot no. 9 which, consistent with campus goals, will provide an 18-hour-per-day attendant parking information center to support the requirements of University Hall; Behavioral Sciences Building; Education, Communications, and Social Work Building; Alumni Hall; and the Pavilion. Construction will begin in September and is scheduled to be completed by December 1986. The contracts are as follows: Division I — General Base Bid Certified Midwest Construction, Inc., Berwyn $144 500 Division II — Plumbing G. F. Connelly Co., Inc., Chicago 21 961 Division III — Heating, Refrigeration and Ventilation The Heat Engineering Company, Countryside 3 829 Division V — Electrical Premier Electrical Construction Co., Chicago 51 601 Total $221 891 A schedule of the bids received has been filed with the secretary of the board for record. Funds for this project are available from the proceeds of the Series 1985 Auxiliary Facilities Revenue Bond issue. On motion of Miss Smith, these contracts were awarded by the following vote: Aye, Mrs. Day, Mr. Forsyth, Mrs. Gravenhorst, Mr. Hahn, Mr. Howard, Mr. Logan, Mr. Madden, Mrs. Shepherd, Miss Smith; no, none; absent, Governor Thompson. (The student advisory vote was: Aye, Mr. Filip, Mr. Starkeson; no, none.)