UIHistories Project: A History of the University of Illinois by Kalev Leetaru
N A V I G A T I O N D I G I T A L L I B R A R Y
Bookmark and Share



Repository: UIHistories Project: Board of Trustees Minutes - 1988 [PAGE 262]

Caption: Board of Trustees Minutes - 1988
This is a reduced-resolution page image for fast online browsing.


Jump to Page:
< Previous Page [Displaying Page 262 of 629] Next Page >
[VIEW ALL PAGE THUMBNAILS]




EXTRACTED TEXT FROM PAGE:



252

Division HIS — Environmental Walk-In Freezer Lab-Line Instruments, Inc., Melrose Park

BOARD OF TRUSTEES

[April 9

Rooms/

Base Bid A l t P-3 Alt. P-4 Alt. P-6

... % ... ... ...

114 14 45 39

778 831 567 764 214 940 $26 298 682

Total

Funds are provided from private gift funds through the University of Illinois Foundation and from funds appropriated by the State of Illinois. The three construction award phases of the project are as follows: Bid Package # / — Site clearance, demolition, excavation, caissons, foundations, perimeter drainage, and waterproofing. (Awarded November 13, 1986) Bid Package #2—Structural steel, concrete, metal deck, stairs, fireproofing, and elevators. (Awarded January 15, 1987) Bid Package # 3 — Balance of construction, except terrazzo-marble, flooring, and vertical isolation doors divisions which will be rebid and the site development work which is being deferred until early 1988. A schedule of the bids received has been filed with the secretary of the board for record. O n m o t i o n of M r . H a h n , these contracts w e r e awarded by t h e followi n g v o t e : Aye, M r s . Calder, M r . Forsyth, M r s . Gravenhorst, M r . H a h n ,

Mr. Howard, Mrs. Shepherd, Miss Smith, Mr. Wolff; no, none; absent, Mr. Logan, Governor Thompson. (The student advisory vote was: Aye, Mr. Filip, Mr. Starkeson; no, none.)

Authority to Approve "General Condition Items," Beckman Institute, Urbana

(19) Turner Construction Company of Chicago was employed as construction manager for the Beckman Institute under authority of the board in November 1985. The construction manager provides services to the owner and the architect from the beginning of design through completion of construction, but does not undertake the actual construction work with its own. staff nor does it contract for such work. As there is no general contractor for this project, the responsibility for providing "general condition items" (such as tools and supplies, temporary roads, water, weather protection, temporary light and power, material and personnel hoists, site plumbing, dirt chutes, pumping, general protection, etc.) is not included in any of the construction contracts. Turner Construction Company has agreed to arrange for the contractors to provide these items as needed. The total cost of the items has been budgeted at $1 million for the duration of the construction period, i.e., until December 1988. The cost of some of the items is expected to exceed the delegated authority limit of $25,000. In order not to delay the project, it is important that authority to approve such items be delegated to the comptroller. Accordingly, the president of the University, with the concurrence of the appropriate administrative officers, recommends that the comptroller be authorized to approve contract change orders to the appropriate contractors to provide for general condition items of work within the budgeted $1 million total.