1996]

UNIVERSITY OF ILLINOIS

535

A schedule of the bids received has been filed with the secretary of the board for record. The vice president for business and finance concurs. I recommend approval.

On motion of Mrs. Gravenhorst, this recommendation was approved by the following vote: Aye, Mrs. Calder, Mr. Engelbrecht, Dr. Gindorf, Mrs. Gravenhorst, Mr. Lamont, Ms. Reese; no, none; absent, Dr. Bacon, Governor Edgar, Ms. Lopez, Mrs. O'Malley. (The student advisory vote was: Aye, Mr. Rose; no, none; absent, Mr. Malone, Mr. Mathew.)

Contract for Re-roofing and Masonry Restoration, Associated Health Professions Building and Re-roofing, College of Nursing Building, Chicago

(17) The interim chancellor at Chicago recommends the award of a contract for $369,747 to F.J.A. Christiansen Roofing Corp., Carol Stream, for the re-roofing and masonry restoration of the Associated Health Professions building and the re-roofing of the College of Nursing building at the Chicago campus. Competitive bidding procedures in accordance with the Illinois Purchasing Act were followed. The project for the Associated Health Professions building consists of removing the existing roofing system down to the structural deck, installing a vapor barrier, and providing insulation and a built-up roofing membrane. The project also includes masonry restoration and tuckpointing of parapet and exterior walls, and the resealing of coping joints and new counter flashing. The College of Nursing project consists of removing the existing roofing system, installing a vapor barrier, providing insulation, repairing/re-sealing of coping joints, and performing asbestos abatement work. A schedule of the bids received has been filed with the secretary of the board for record. Funds for this contract are available in the Institutional Funds Operating Budget for Deferred Maintenance of the Physical Plant of the Chicago campus. The vice president for business and finance concurs. I recommend approval.

On motion of Mrs. Gravenhorst, this recommendation was approved by the following vote: Aye, Mrs. Calder, Mr. Engelbrecht, Dr. Gindorf, Mrs. Gravenhorst, Mr. Lamont, Ms. Reese; no, none; absent, Dr. Bacon, Governor Edgar, Ms. Lopez, Mrs. O'Malley. (The student advisory vote was: Aye, Mr. Rose; no, none; absent, Mr. Malone, Mr. Mathew.)

Contracts for Repairs, Minor Remodeling, and New Construction, Urbana

(18) On April 13, 1995, the Board of Trustees approved the award of the following cost-plus contracts for repairs, minor remodeling, and new construction at the Urbana campus for the fiscal year ending June 30, 1996, with an option to extend the contracts from July 1, 1996, to June 30, 1997, under the same terms and conditions, subject to approval by the Board of Trustees.