146

BOARD OF TRUSTEES

[January 15

On motion of Mrs. Gravenhorst, these contracts were awarded by the following vote: Aye, Dr. Bacon, Mr. Boyle, Mrs. Calder, Dr. Gindorf, Mr. Grabowski, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Ms. Reese; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Mr. Begovich, Mr. Lawless; no, none.)

Contract, Metal Storage Building, Urbana

(22) The president of the University, with the concurrence of the appropriate administrative officers, recommends the award of a contract for $95,905 to SturdiBuilt Corporation, Charleston, the lowest responsible bidder, on its base bid plus acceptance of alternates, for the construction of a 9,120 square foot metal storage building at the Urbana campus. The $102,405 project consists of furnishing all labor, materials, and equipment necessary for the construction of a 9,120 square foot metal-clad frame building located on Wright Street extended at Hazelwood Drive, Champaign. The building is for unheated storage; and one-third of the space will be used by general University departments, one-third will be used by the Office of Telecommunications, and onethird will be used by the Division of Campus Parking. Funds are available in the institutional funds budget of the Urbana campus, the Office of Telecommunications, and the Division of Campus Parking. A schedule of the bids received and a description of the alternates have been filed with the secretary of the board for record.

On motion of Mrs. Gravenhorst, this contract was awarded by the following vote: Aye, Dr. Bacon, Mr. Boyle, Mrs. Calder, Dr. Gindorf, Mr. Grabowski, Mrs. Gravenhorst, Mr. Lamont, Ms. Lopez, Ms. Reese; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Mr. Begovich, Mr. Lawless; no, none.)

Contracts, Campus Bookstore and Office Building, Urbana

(23) The president of the University, with the concurrence of the appropriate administrative officers, recommends award of the following contracts for the construction of the $13.4 million campus bookstore and office building at the Urbana campus. The award in each case is to the lowest responsible bidder on its base bid plus acceptance of the indicated alternates.' Division I — General Williams Brothers Construction, Inc., Peoria

Base Bid Alt. G-l

$6 384 000 20 000 $ 6 404 000

(Note: Bids were also received for Division IV — Ventilation and Air Distribution work. After review of the bids of all of the bidders (total of seven), the architect discovered that four did not include all of the work required by an addendum within their bids. In that there may have been a misunderstanding, the architect has recommended that the division of work be rebid. The Office for Capital Programs and university counsel concur. This delay will not affect the project schedule.)