56

board of trustees

[September 17

nate N o . 4 be let as a separate contract at a later date w h e n definite plans and specifications can be prepared and checked b y the state architect's office. W e have investigated the qualifications of the Davis Construction C o m p a n y and find them to be responsible bidders. W e enclose herewith their financial statement. Very truly yours,

Granger & Bollenbacher By J. O. Merrill

HEATING BIDS Medical and Denial College Laboratories Davis Const. United Plbg. Company br Heating L. H. Prentice H. P. Reger Base bid, including Johnson Reg. and pipe covering; not including outside lines.. 469 095 $71 500 $71 571 $74 409 (Note A) Alternate No. 1, add for National Reg.... 340 343 400 Alternate No. 1, add for Powers Reg 3 750 3 750 4 125 Alternate No. 2, deduct for omission of pipe covering 5 700 8 058 8 000 8 000 Alternate No. 3, deduct for fees Alternate No. 4, add for outside lines 3 771 1 571 4 200 2 300 Total base bid plus Alternate No. 4 73 766 73 071 75 771 76 799 Note A—United Plumbing & Heating Company's bid does not state which temperature control system is included in Base Bid. GaUaheT W m . V. Hoier W m . A. Poie Chas. E. Evans and Speck Base bid, including Johnson Reg. and pipe covering; not including outside lines.. £74 800 £78 486 £78 49s #8o 388 Alternate No. 1, add for National Reg 343 440 343 Alternate No. 1, add for Powers Reg 1 350 4 400 3 750 Alternate No. 2, deduct for omission of pipe covering 5 000 8 too 8 642 8 410 Alternate No. 3, deduct for fees Alternate No. 4, add for outside lines 1 800 2 725 1 384 1 900 Total base bid plus Alternate No. 4 76 600 81 211 79 879 82 288 W.J. Economy Carl J. S. J. Gemeny Plbg. 6r Htg. C. W. Johnson Stein Co. Reynolds Co. Base bid, including Johnson Reg. and pipe covering; not including outsides lines £83 000 £83 324 £83 500 $84 000 00 t&S 999 Alternate No. 1, add for National Reg. 343 425 Alternate No. 1, add for Powers Reg. 3 750 4 230 4 12s Alternate No. 2, deduct for omission of pipe covering 8 200 9 855 8 500 9 734 50 8 125 Alternate No. 3, deduct for fees 50 20 Alternate No. 4, add for outside lines 5 250 2 100 r 500 3 343 00 3 200 Total base bid plus Alternate No. 4.. 88 250 85 424 85 000 87 343 00 89 199 There are certain alternates with respect to temperature regulations and pipe covering, and the contract will be so drafted as to reserve the right to accept any of these alternates at a later date. O n motion of M r . Armstrong, the contract for heating w a s awarded to the Davis Construction C o m p a n y , the lowest bidder, as recommended.

SASH FOR MEDICAL AND DENTAL. LABORATORIES

In connection with the original bids for the General Contract for the Medical and Dental detail, it of manufacturers. T then figures s from ationdirectly fromentire building. alternate proposalsreceived, whichthey buyingbof the bacher of and w thethe windows. schedule and w a letterbeen a e explains sash sash for part appears that the Since h e of savingreceived fordfor b directly Bollenarchitects,for the s 1930, with at considerable bids havetakenm forrecord. andof y i n u m sash Augusta4, submitted an this point followingwalsoreceived Granger use thealumsteel inLaboratories Building, a A n alternate was a can be takenthe omission these situ-