It is also recommended that the project architect, Severns, Reid & Associates, Inc., be employed for contract administration services required during the construction phase of the project on a fixed-fee basis of $15,750; and to provide the required on-site observation on an hourly basis, estimated at $19,000, plus authorized reimbursements estimated to be $12,250. T h e work consists of removing and replacing the existing 23-year-old indoor Tartan track and infield with a new polyurethane track surface. T h e track and the corresponding asphalt base course will be realigned into a new six-lane, 200-meter facility conforming to current NCAA indoor track standards; with infield facilities for the pole vault, long jump, triple jump, shotput, and high j u m p events. Permanent telescoping bleachers will be installed, with a seating capacity of 1,964. Permanent pedestrian corridors will be established on the east and west ends of the arena and an interim corridor will be established on the north side to direct pedestrian traffic around the arena and to better control access thereto. Funds are available through the proceeds of the Auxiliary Facilities System, Series 1991 Revenue Bond issue. A schedule of the bids received, a description of the alternates, and the architect's hourly rate schedule have been filed with the secretary of the board for record.

On motion of Mr. Boyle, these contracts were awarded by the following vote: Aye, Dr. Bacon, Mr. Boyle, Mrs. Calder, Mr. Downey, Mr. Lamont, Ms. Reese, Mrs. Shepherd; no, none; absent, Governor Edgar, Mr. Grabowski, Mrs. Gravenhorst. (The student advisory vote was: Aye, Ms. Caporusso, Mr. Mitchell; no, none.)

Contracts, North Campus Oval Phase I I/Computer and Systems Research Laboratory Site Development, Urbana

(12) T h e president of the University, with the concurrence of the appropriate administrative officers, recommends award of the following contracts for construction of the North Campus Oval Phase I I/Computer and Systems Research Laboratory (CSRL) site development at the Urbana campus. T h e award in each case is to the lowest base bidder plus acceptance of the alternates. Site Development Division I — General C. Iber & Sons, Inc., Peoria Base Alt. Alt. Alt. Alt. Bid 1 2 3 4 $153 700 2 142 9 500 4 570 10 200 $180 112 Division V — Electrical Glesco Electric, Inc., Urbana Base Bid Alt. 1 $ 38 323 4 519 42 842 Landscape Division I — General Cornbelt Landscaping, Pesotum

Base Bid Alt. 1

$106 708 12 900 119 608 $342 562