470

BOARD OF TRUSTEES

[February 13

These contracts consist of building demolition, building excavation, foundation work, cast-in-place concrete and fabrication and erection of the building steel frame and metal decks. T h e proposals for the balance of the work will be in subsequent bid groups. Gift funds are available through the University of Illinois Foundation. A schedule of the bids received and a description of the alternate have been filed with the secretary of the board for record.

On motion of Dr. Bacon, these contracts were awarded by the following vote: Aye, Dr. Bacon, Mr. Boyle, Mrs. Calder, Mr. Downey, Mr. Grabowski, Mrs. Gravenhorst, Mr. Lamont, Ms. Reese, Ms. Shepherd; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Ms. Caporusso, Mr. Mitchell; no, none.)

Contract, Harker Hall Reconstruction, Urbana

(9) T h e president of the University, with the concurrence of the appropriate administrative officers, recommends that the University of Illinois Foundation be requested to provide the funds necessary for the University to award a contract for $54,000 to Duce Construction Company, Tolono, for the reconstruction of Harker Hall at the Urbana campus. T h e award is to the low bidder on its base bid. T h e work consists of installing precast concrete pavers, retaining walls, and a fountain. Private gift funds are available through the University of Illinois Foundation. A schedule of the bids received has been filed with the secretary of the board for record.

On motion of Dr. Bacon, this recommendation was approved by the following vote: Aye, Dr. Bacon, Mr. Boyle, Mrs. Calder, Mr. Downey, Mr. Grabowski, Mrs. Gravenhorst, Mr. Lamont, Ms. Reese, Ms. Shepherd; no, none; absent, Governor Edgar. (The student advisory vote was: Aye, Ms. Caporusso, Mr. Mitchell; no, none.)

Increase in Contract, Law Building Addition and Remodeling, Urbana

(10) In November 1990 and May 1991, the Board of Trustees authorized the employment of O'Donnell, Wicklund, Pigozzi and Peterson, Architects, Inc., Deerfield, to provide the architectural/engineering services required from the program definition/concept development phase through the bidding phase of the Law Building Addition and Remodeling project at the Urbana campus. In order to complete construction by the fall semester of 1993, it will be necessary to phase the planning and construction. To this end, the architect will be required to develop multiple bid packages as well as alternates not anticipated in the original project. Accordingly, the president of the University, with the concurrence of the appropriate administrative officers, recommends that the contract with O'Donnell, Wicklund, Pigozzi and Peterson, Architects, Inc., Deerfield, be increased by $58,700 to provide the services described above. Funds are available from private gift funds through the University of Illinois Foundation. Upon receipt of satisfactory bids, the board will be asked to approve construction contracts and to employ the architect/engineer through the construction phase of the project.