1990]

UNIVERSITY OF ILLINOIS

99

This project includes the renovation of the north central guest rooms and their conversion into meeting rooms on the fourth floor of the Illini Union's north building, 7,200 square feet, including the renovation of toilet facilities on this floor. T h e work consists of demolition and removal of existing walls, partitions, and restrooms; the installation of new partitions and doors; the upgrading of building ventilation, airconditioning, and sprinkler systems; and new finishes in the affected areas. It is further recommended that the firm of T h e Troyer Group, Mishawaka, Indiana, be employed for the professional architectural and engineering services required during the construction phase of the project at a fixed fee of $34,100 for contract administration and for on-site observation which will be on an hourly basis and is estimated to be $10,000. Funds are available in the Auxiliary Facilities System Repair and Replacement Reserve account and from the Restricted Funds operating budget of the Illini Union. A schedule of the bids received and a description of the alternate have been filed with the secretary of the board for record.

On motion of Ms. Reese, these contracts were awarded by the following vote: Aye, Dr. Bacon, Mr. Boyle, Mrs. Calder, Mr. Grabowski, Mrs. Gravenhorst, Mr. Hahn, Ms. Reese, Mrs. Shepherd, Mr. Wolff; no, none; absent, Governor Thompson. (The student advisory vote was: Aye, Mr. Forbes, Ms. Kelly; no, none.)

Contracts, Lower Level Remodeling, Illini Hall, Urbana

(16) T h e president of the University, with the concurrence of the appropriate administrative officers, recommends the award of the following contracts for the remodeling of the lower level of Illini Hall at the Urbana campus. T h e award in each case is to the low base bidder plus acceptance of the indicated alternates. Division I — General Tri-R Development Co., Champaign Base Bid Alt. G-l Alt. G-2 $247 700 9 840 18 850 $276 390 Division II — Plumbing A 8c R Mechanical Contractors, Inc., Urbana Division HI — Heating, Temperature Control, and Refrigeration A 8c R Mechanical Contractors, Inc., Urbana Division IV — Ventilation and Air Distribution A 8c R Mechanical Contractors, Inc., Urbana Division V — Electrical Witte Electric Company, Champaign Total

Base Bid

31 200

Base Bid

104 600

Base Bid Base Bid

68 824 122 880 $603 894

It is also recommended that the contracts for the divisions of work, other than the contract for general work, be assigned to the contractor for general work. This project includes the remodeling of approximately 11,500 square feet of basement space in Illini Hall for four general classrooms; a CSO-managed open computer laboratory and administrative training suite (with computer labs and seminar